The long-awaited new Upper Coomera Branch Library, on the corner of Abraham and Reserve Roads at Upper Coomera, opened on 29 April.

Customers can select Upper Coomera as the pick up location for their holds. Customers who haven't visited a library in recent months, please bring with you identification with proof of residential address so that we can ensure our records are accurate. We look forward to welcoming you and your family to this wonderful new facility that includes Cr Gates' divisional office, a Customer Service Office, a multi-purpose community centre and aquatic facilities. 

Details of the opening celebrations will be available from the centre in coming weeks. For further information, please contact Library Administration on (07) 5581 6788.

90 Reserve Road 
Upper Coomera  QLD  4209

Phone: (07) 5582 9300
Fax: (07) 5573 6213
Email: lcs@goldcoast.qld.gov.au
Ask a librarian online contact form

How do I get there?

View map (courtesy of Google Maps)

Opening hours

  • Monday: 9am - 6pm
  • Tuesday: 9am - 6pm
  • Wednesday: 9am - 6pm
  • Thursday: 9am - 7pm
  • Friday: 9am - 6pm
  • Saturday: 9am - 4pm
  • Sunday: Closed

Images will be updated as development on the Upper Coomera Community Centre progresses.

Find the link for the draft Concept Plan below.

After delays due to the wet weather, there is now a lot of activity at the Upper Coomera Centre construction site.

Installation of 150 concrete piles around the perimeter of the building are complete. Construction of the concrete ground beams around the perimeter are due to be completed by the end of May. The tilt-up concrete wall panels currently being constructed on site are also due to be completed by the end of May. Structural steelwork is being progressively manufactured off site. Erection of the wall panels and structural steel is programmed to commence in early June.

This web page will be updated regularly with new images of construction.

Click each image to view a larger version.

Upper Coomera Community Hub and Library development

Upper Coomera Community Hub and Library development

Upper Coomera Community Hub and Library development

Upper Coomera Community Hub and Library development Upper Coomera Community Hub and Library development Upper Coomera Community Hub and Library development

Ground works

Click each image to view a larger version.

Upper Coomera Community Hub and Library development Upper Coomera Community Hub and Library development Upper Coomera Community Hub and Library development Upper Coomera Community Hub and Library development

26 July 2012

Click each image to view a larger version.

Upper Coomera Community Hub and Library development Upper Coomera Community Hub and Library development Upper Coomera Community Hub and Library development

September 2012 Community Update

Construction at the site of the new Upper Coomera Branch Library and Community Hub is well underway.

The floor for the Branch Library and Community Centre is down and all the structural steel work is completed. Services including fire, data, power, plumbing and water are currently being roughed in.

The structural steel and roof for the aquatic centre is near completion and work on the swimming pool has commenced.

With the stable weather, construction is well on schedule and Gold Coast City Council is still looking forward to an opening date in early autumn 2013.

Construction updates will also be posted on our library Facebook page. To receive the updates, like us on Facebook. For any questions relating to the project, please phone (07) 5581 6788.

Thank you for your ongoing support and patience while Council completes this exciting new facility.