Water main replacement

Hours of work:
Night shifts Monday to Friday

See references below.

Project details:

The City will be constructing new water mains at the below locations as part of the Infrastructure Renewal program.

Works will be carried out in three stages:

  • pipe laying
  • re-connections
  • and restoration.

During the re-connection stage, temporary water shutdown will be required and affected residents will be advised by notification letters.

Public impact:

Night shift, construction noise, dust and traffic.

Areas affected:

Suburb Division Streets affected Project duration Reference
Helensvale 2 Batlow Court 1 March to 30 March 2018 68242798, 68252544
Nerang 5 Price Street 23 April to June 2018 68630035, 68623173
Mudgeeraba 9 Mark Way 13 March to 3 April 2018 68424816, 68425842