Annual minor culvert renewal program 2024-2025

  • Project typeStormwater
  • Project value$1.483 million
  • Project scheduleMarch 2024 to June 2025
culvert-2024.jpg

We continue to renew culverts (under-road stormwater drainage pipes) across the city that are close to the end of their serviceable life.

We maintain over 2600 kilometres of stormwater drainage with an ongoing upgrade and renewal program. These works are part of our stormwater drainage annual capital works program.

Construction details

Existing under-road drainage pipes will be excavated and replaced with new pipes.

Community impacts during construction

  • Works will be completed between 7am and 5pm, Monday to Friday and take approximately 10 to 20 days at each site, weather permitting.
  • Some partial road closures will be necessary during construction. There will be no full road closures and access will be maintained for residents and motorists.
  • Traffic controllers will be on duty to help and some traffic delays are expected. Please follow all signage.
  • We will be working to ensure disruptions are kept to a minimum. However, nearby residents may notice construction noise at times.

Benefits for the community

  • Reduced risk of flooding roads and property in catchment areas
  • Improved water drainage following weather events
  • Improved safety for the community

2024–2025 program

Approximate location Suburbs Start date
32 Pimpama-Jacobs Well Road Pimpama 1 March 2024
31 Austinville Road Austinville 8 July 2024
188 Shaws Pocket Road Cedar Creek 27 September 2024
1332 Tallebudgera Creek Road Tallebudgera Creek 12 December 2024
68 Billabirra Crescent Nerang 10 February 2025
1 Palmer Drive Labrador 14 February 2025
211 Petsch Road Tallebudgera 6 March 2025
376 Piggabeen Road Currumbin Valley 1 May 2025
186 Trees Road Tallebudgera 6 May 2025