Coolangatta – Rutledge Street retaining wall works
- Project typeRoads & transport
- Project value$1.05 million
- Project scheduleMarch to June 2026 (weather permitting)
We are upgrading the retaining wall on Rutledge Street, between Tweed Street and Staptylton Street in Coolangatta. The upgrade will improve slope stability, road safety and drainage. Works include closing sections of the road and traffic detours.
Construction details
- Replace existing retaining wall
- Reconstruct kerb and channel on the lower service road
- Install new kerb and channel along Rutledge Street where the guardrail is currently located
- Replace guardrail
- Reconstruct road pavement above the retaining wall
- Upgrade stormwater drainage, including a new gully pit and stormwater pipe
- Remove existing vegetation along the wall
Impact during construction
- Work hours: 7am to 5pm, Monday to Friday
- Rutledge Street will operate to local traffic only between Tweed Street and Stapylton Street
- Temporary road closures and detours will be in place
- Parking near the works area will be restricted
- Access to property along the lower service road may be affected at times
- You may notice construction noise, truck movements, dust and vibration
Residents directly affected by the works will receive updates and notifications as works progress.
Benefits for the community
- A stronger, modern retaining wall built for long‑term stability
- Safer road conditions with upgraded kerb, pavement and guardrail
- Better stormwater management to support local drainage
- Reduced maintenance needs and improved resilience of the road corridor
Location
31 to 39 Rutledge Street, Coolangatta 4225
View map and directions on Google
-28.1711258032772, 153.53199130045863
31 to 39 Rutledge Street ,
Coolangatta 4225
31 to 39 Rutledge Street ,
Coolangatta 4225
Coolangatta – Rutledge Street retaining wall works