Hollywell – Holly Avenue stormwater drainage renewal

  • Project typeStormwater
  • Project value$120,000
  • Project scheduleNovember 2023 to January 2024
Stormwater drainage pipes

Works are underway to upgrade the stormwater drainage system in front of 8 Holly Avenue, Hollywell.

Construction details

  • Install new 600mm x 300mm underground box culverts between the kerbside inlets in front of 8 Holly Avenue
  • Reinstate any assets impacted by the work, including kerb and channel, pavement, asphalt surfacing, fences, and areas including turf

Impacts during construction

Construction will take up to 6 weeks (weather permitting). Works will take place between 7am and 5pm Monday to Friday.

There will be a temporary loss of street parking spaces around the work site. Partial lane closures will be in place during working hours, with traffic management in place. Emergency access and pedestrian access to properties will be always maintained.

We will ensure disruptions are kept to a minimum. However, residents may notice construction noise, dust and vibration at times. We will do our best to minimise disruptions and thank you in advance for your patience.

Benefits to the community

  • Improved safety and function of the drainage network system
  • Reduced ongoing maintenance requirements and costs

Area of work