Lower Beechmont - North Road - retaining wall

Commencing: April 2019
Completed: October 2019
Total project cost: $880,000
Project information
The North Road retaining wall in Lower Beechmont has been remediated to ensure the embankment is stabilised.
Construction details
- demolish existing timber retaining wall
- construct concrete pile retaining wall
- reinstatement of road pavement
- guardrail installation.
Community benefits
- stabilisation of failing road embankment
- improved road safety
- improved resilience to landslides and high volume rainfall events.
More information
For more information contact the Project Manager on 07 5667 3760.
Extent of works