Sandy Creek sewerage augmentation

Worker checking equipment

Commencing: October 2019
Completion: October 2020
Hours of work: Monday to Friday 7am to 5pm
excluding public holidays.

Project details

The Sandy Creek Industrial Precinct has been identified by the City as a priority development area to encourage industry to invest in the area and promote development. At present, the precinct is only partially serviced with water and sewer services, and approximately 137 hectares of industrial land is without connection to the City’s sewerage network.

The Sandy Creek sewerage augmentation project will enable the connection of twenty-eight industrial zoned properties, supporting growth and investment in the area.

The project as a whole consists of the construction of:

All infrastructure will connect to an existing pump station located on Burnside Road.

Public impact

Areas affected

Suburb Division Streets affected
Stapylton, Ormeau Division 1 Burnside Road, Christensen Road, Greyhound Road, Prairie Road

Extent of works

An approximation of the area of works.

 