Water main replacement

Hours of work
7am to 5pm, night shifts
Monday to Friday

See references below.

Project details

City of Gold Coast is constructing new water mains at the below locations as part of the infrastructure renewal program.

Works will be carried out in three stages:

  • pipe laying
  • reconnections
  • restoration.

During the reconnection stage, temporary water shutdown will be required and affected residents will be advised by notification letters.

Public impact

It is expected that the work will produce construction noise, dust and will impact local traffic conditions. Partial road closures may be necessary and motorists and pedestrians are urged to follow the direction of traffic control officers on site.

Areas affected

Suburb Division Streets affected Project duration Reference
Currumbin Waters 14 Station Street 4 November 2019 to 13 December 2019 74170307, 74820518
Gaven 5 Peony Way 25 November 2019 to 23 December 2019 75022903, 74979349
Runaway Bay 4 Bulolo Avenue 2 December 2019 to 23 December 2019 75053749