Water main replacement – Burleigh Heads

Project details

Under our infrastructure renewal program, the City will be constructing a new water main at the intersection of Acanthus Avenue, Diana Avenue and Symonds Road, Burleigh Heads.

The pipe main works will be carried out in stages:

  • installation of by-pass valves
  • pipe laying and
  • restoration.

During the installation of by-pass valves, temporary water shutdown will be required, and affected residents will be advised in advance by a separate notification letter.

Hours of work

7am to 5pm Monday to Friday

Public impact

Construction noise and dust, traffic, possible interruption to water supply

Areas affected

Suburb Division Streets affected Project duration Reference
Burleigh Heads 13 Intersection of Acanthus Avenue, Diana Avenue and Symonds Road, Burleigh Heads. 22 March to 19 April 2021 A64936738